Driving the Jalandhar Ring Road: Comparing Construction Progress from March to July 2026

This article details the construction progress of the Jalandhar Ring Road, connecting the Amritsar and Pathankot Highways.

The Ghulatis On The Go team embarked on a journey to document the latest construction updates of the Jalandhar Ring Road, specifically the stretch connecting the Amritsar Highway to the Pathankot Highway. This video, recorded in July 2026, provides a comprehensive comparison with previous footage from March 2026, highlighting the significant advancements made in just four months. The objective was to offer viewers a ground-level perspective of the ongoing infrastructure development, showcasing the transformation of key sections of the ring road.

The journey commenced from the Suranussi area of Jalandhar, known for its green belt, before transitioning onto the Jalandhar-Amritsar National Highway. The initial segment of the drive revealed a well-maintained, six-lane highway adorned with bougainvillea on the central verge and efficient street lighting, indicating a top-notch road condition. The team noted the smooth ride, even at speeds of 70-80 km/h, underscoring the quality of the completed sections. This initial stretch provided a stark contrast to the areas still under heavy construction, setting the stage for the detailed progress report that followed.

Amritsar Highway to Jalandhar Ring Road Crossing

Upon reaching the Jalandhar-Amritsar National Highway, the team observed a sign indicating Amritsar was 70 kilometers away. Their destination, however, was the Jalandhar Ring Road bypass spur, located before Beas. The drive along this section of the highway showcased the impressive infrastructure, including the six-lane road and well-lit streets. The central verge, adorned with bougainvillea, added to the aesthetic appeal of the highway.

A significant point of interest was the Jalandhar Ring Road crossing the Amritsar Highway. The team slowed down to highlight the concrete trusses that had been placed on the flyover, a notable development since their last visit in March 2026. At that time, these trusses were absent, indicating substantial progress in the construction of this crucial interchange. The visual comparison between the current state and the March footage clearly demonstrated the rapid pace of work.

Progress on the Jalandhar Ring Road Spur

After crossing under the partially constructed flyover, the team made a U-turn to access the Jalandhar Ring Road. This section of the road, intended for ascending onto the bypass, was still under construction. The video captured various construction machinery, including cranes, and showed workers actively engaged in preparing the site for further development. The retaining walls were fully constructed, and earthwork was in progress to level the road, indicating that the project was moving forward despite the challenges.

A direct comparison with the March 2026 footage revealed that this area, which was previously an empty plot, was now bustling with activity and heavy machinery. The progress in constructing the approach ramps for the flyover was evident, with significant earthwork and structural preparations underway. This segment of the journey underscored the commitment to completing the ring road, even in areas requiring extensive civil engineering work.

Blacktop Work and Road Conditions

Further along the Jalandhar Ring Road, the team encountered sections where blacktop work had already commenced. This was a major improvement compared to March 2026, when these stretches were unpaved and covered in gravel. The newly laid blacktop provided a smooth driving surface, allowing the team to maintain a good speed without experiencing any jerks or discomfort. The quality of the road surface suggested that the final layers of asphalt would soon be applied, bringing these sections closer to completion.

The video also showed instances where locals were utilizing the central verge of the unfinished expressway to dry grains. While this is a common practice in rural areas where new infrastructure is not yet fully operational, it also highlights the need for timely completion to ensure the intended use of the highway. Despite these temporary uses, the overall impression was one of continuous progress, with significant portions of the road already paved and ready for the final touches.

Connecting to Pathankot Highway and Future Outlook

As the team continued their drive, they observed that the blacktop work extended for considerable distances on both sides of the road, indicating a consistent effort to complete the paving. The retaining walls along these sections were also fully completed, suggesting that the structural integrity of the elevated road was in place. The smooth ride and the visible progress instilled confidence in the project's eventual completion.

The journey culminated in connecting to the Pathankot Highway, effectively linking the Amritsar and Pathankot Highways via the Jalandhar Ring Road. While some sections still required the final layer of asphalt and additional earthwork, the overall transformation since March 2026 was remarkable. The team noted that approximately 70% of the Jalandhar Ring Road project was complete, with the remaining 30% still in various stages of development. The rapid progress, particularly in laying the blacktop and constructing the flyovers, suggests that the ring road will soon be fully operational, significantly improving connectivity and reducing travel times in the region.

Practical Takeaways

  • Significant Progress: The Jalandhar Ring Road project has seen substantial progress between March and July 2026, particularly in the construction of flyovers and the laying of blacktop.
  • Improved Connectivity: Once fully operational, the ring road will provide seamless connectivity between the Amritsar and Pathankot Highways, bypassing city traffic.
  • Quality Construction: Completed sections of the highway, including the six-lane road and street lighting, demonstrate high-quality construction.
  • Ongoing Work: While major strides have been made, some sections still require final paving and earthwork, indicating that construction is ongoing.
  • Local Utilization: Unfinished sections of the expressway are temporarily used by locals for drying grains, highlighting the need for project completion.
  • Future Benefits: The completed ring road is expected to enhance regional infrastructure, facilitate smoother travel, and contribute to economic development.

Watch the Original Journey

This article is connected to the original Ghulatis On The Go video below. Watch it for the complete visual experience and conversations from the road.

Key moments from the video

  • 00:13: The video provides a construction update of the Jalandhar Ring Road from Amritsar Highway to Pathankot Highway.
  • 00:24: The route was previously shown in March, and there has been significant progress since then.
  • 01:16: A sign indicates Amritsar is 70 kilometers away on NH3.
  • 02:18: The concrete trusses on the Jalandhar Ring Road crossing Amritsar Highway were not present in March.
  • 02:40: Construction machinery is visible at the climbing area of the bypass, indicating ongoing work.
  • 04:18: A comparison shows that a stretch of the road, previously gravel, now has blacktop laid.
  • 05:40: Locals are using the central verge of the unfinished expressway to dry grains.
  • 06:07: The car is driving at 70-80 km/h on the newly laid blacktop without any jerks, indicating good road quality.
  • 07:45: Earthwork is being done to fill the road, allowing vehicles to drive on top of the ring road.
  • 08:59: A comparison shows that a previously unpaved section of the road is now blacktopped.
  • 13:00: The Gurudwara Sachkhand Ballan Ji is visible on the left side of the road.
  • 16:48: Approximately 70% of the Jalandhar Ring Road project is complete, with 30% still pending.